By Ayla Ozturk
VISALIA CA– On Friday, February 10, 2023, Redwood High School Principal Dr. Amanda Richard provided an update on the ongoing gymnasium construction.
The construction team painted the walls white and did other interior work. You can see pictures of the updates here.
According to Dr. Richard, the locker rooms should be available sometime this week.
Yesterday, Monday, February 13, the construction team began tearing the gymnasium’s old floor out and replacing it. This will take approximately six weeks.
After the new floors are placed, the new bleachers will be installed.